Field guide · 2 min read
TG20:21 scaffold checks
How we inspect tube-and-fitting scaffolds against the NASC TG20:21 guidance, and the checks your site team can make every day.
01What TG20:21 is
TG20:21 is the NASC's good-practice guidance for tube-and-fitting scaffolds, widely specified on Saudi projects. A scaffold that matches one of its compliant set-ups can be built from the guidance alone. Heavy loading bays, tall sheeted scaffolds and cantilevers need a design from a competent scaffold designer before they go up.
02When to inspect
- Before first use, once the erector hands it over.
- At least every seven days while it is in use.
- After any change, such as an alteration, a removed tie or an impact.
- After strong wind or anything else that could affect its stability.
If your client's site rules ask for more frequent checks, theirs apply.
03What we check
- Foundations. Sole boards and base plates on firm, level ground, with nothing undermining them.
- Standards, ledgers and transoms. Plumb, level and correctly spaced, with all couplers tight.
- Bracing. Façade and ledger bracing complete and in the right places.
- Ties. The tie pattern matches the design or compliance sheet, and ties are tested where the design requires.
- Platforms. Fully boarded, boards supported and secured, with no gaps or trip hazards.
- Edge protection. Guardrail at least 950 mm high, an intermediate rail leaving no gap over 470 mm, and 150 mm toe boards.
- Access. Ladders tied and rising about 1 m above the landing, or a stair tower.
- Loading and sheeting. Only where the design allows for the extra load and wind.
04Tags at access points
Each inspected scaffold gets a SMAT tag at its access points showing who inspected it, when, and when the next inspection is due. A scaffold that fails is tagged "Do not use" until the defects are fixed.